SCOPE OF WORKS

On August 2nd, 2018, Caramondani - Bellingham LTD signed an agreement with M.M. Makronisos Marina LTD for the execution of the EPC/ Turnkey contract for floating doackage at the project:

"Development of Ayia Napa Marina, WP1: Marine works, Infrastructure, Essential Building, Dry Stack and Port Facilities"

Caramondani - Bellingham LTD assigned to Archimedes S.A. - Cyprus Branch certain works of the aforementioned project, namely the following services:

1. Welding of piles according to "Pile Slicing Details".

2. Installation of vertical and raked piles (137 in total).

3. Tolerance for pile driving +/- 50 mm.

4. Inclination for all raked piles 4 to 1.

5. All vertical piles driven to +2.40mCD.

6. All raked piles driven to -5.90mCD or -6.70mCD.

7. All raked piles cut underwater.

8. Pile sleeves installed on all vertical piles.

The project was successfully completed and delivered on July 2019.

ARCHIMEDES S.A. - A Leading Heavy Marine and Civil Contractor in Greece
ARCHIMEDES S.A. - A Leading Heavy Marine and Civil Contractor in Greece
ARCHIMEDES S.A. - A Leading Heavy Marine and Civil Contractor in Greece
ARCHIMEDES S.A. - A Leading Heavy Marine and Civil Contractor in Greece