SCOPE OF WORKS
The Company's duties included:
1. Pile Test Execution (2 piles tested offshore and one tested onshore).
2. Offshore borehole execution.
3. Geotechical study issuance.
The Client of the project was J&P Ltd and J&P (Overseas) Ltd. Construction works lasted about three (3) months. The project was completed in September 2012.