SCOPE OF WORKS
The Company's duties included:
1. Basin dredging.
2. Construction of a caisson quay wall at 14 m depth, 350 m length.
3. Construction of relieving prism.
4. Other concrete superstructure.
The Client of the project was the Piraeus Port Authority. Construction works lasted about seven (7) months. The project was completed in March 2014.